We are pleased to present our latest video in the Delay Analysis Series, which focuses on the Impacted As Planned method. In this session, Shadi Juma, Principal Consultant, provides an in-depth examination of how to utilise a high-quality, logic-linked baseline schedule to assess the impact of potential delay events before they occur.
Key topics covered in the video include:
- Baseline Schedule: The importance of establishing an accurate and well-structured baseline as the foundation for delay analysis.
- Impacted As Planned Method: A detailed explanation of overlaying delay events onto the original contractual schedule to forecast project impacts.
- Practical Application: A step-by-step demonstration using a sample project in Primavera P6, where a 14-day delay in excavation layout approval shifts the project’s completion date from April 21, 2024, to May 6, 2024.
- Extension of Time Calculation: An analysis of the difference between the original and impacted completion dates, translating to a measurable extension of time.
- Method Limitations: An evaluation of the strengths and challenges of using the Impacted As Planned method, particularly in scenarios without concurrency.
This video provides a professional, content-rich overview designed to support project managers and industry professionals in understanding and applying delay analysis techniques effectively.