Impacted As Planned

We are pleased to present our latest video in the Delay Analysis Series, which focuses on the Impacted As Planned method. In this session, Shadi Juma, Principal Consultant, provides an in-depth examination of how to utilise a high-quality, logic-linked baseline schedule to assess the impact of potential delay events before they occur.

Key topics covered in the video include:

  • Baseline Schedule: The importance of establishing an accurate and well-structured baseline as the foundation for delay analysis.
  • Impacted As Planned Method: A detailed explanation of overlaying delay events onto the original contractual schedule to forecast project impacts.
  • Practical Application: A step-by-step demonstration using a sample project in Primavera P6, where a 14-day delay in excavation layout approval shifts the project’s completion date from April 21, 2024, to May 6, 2024.
  • Extension of Time Calculation: An analysis of the difference between the original and impacted completion dates, translating to a measurable extension of time.
  • Method Limitations: An evaluation of the strengths and challenges of using the Impacted As Planned method, particularly in scenarios without concurrency.

This video provides a professional, content-rich overview designed to support project managers and industry professionals in understanding and applying delay analysis techniques effectively.