In this 60-second Short, we show how we calculated a total of 47 days of delay using Windows Analysis across three separate windows.
Not all delay events impact the program equally — in some cases, progress delays along the critical path outweigh the event itself. This Short demonstrates a real example of how we assess and justify delay entitlement in a clear and structured way.
▶️ Watch this Short for a practical breakdown, or view the full explainer here.
Windows Analysis Delay Analysis
#DelayClaims #WindowsAnalysis #ConstructionExperts #CSPMConsulting