How a 22-Day Access Delay Shifted Completion in a Building Project

This Short presents a theoretical Windows Analysis scenario involving a substructure access delay in a two-building project.

The delay event — lack of access to Building 1 — led to a 22-day delay to project start, shifting the completion date to 6 September 2024. We break down how this is captured in the first progress update using baseline comparison.

▶️ Watch this Short for a visual scenario walkthrough, or view the full explainer here.

Windows Analysis Delay Analysis

#DelayClaims #WindowsAnalysis #ConstructionExperts #CSPMConsulting